# RVNL: how the business works

> For learning only. Cityfort is not a SEBI-registered adviser and does not recommend buying or selling any security. Prices shown are dated and may be out of date.

Rail Vikas Nigam Limited · NSE: RVNL · BSE: 542649 · Sector: Construction

Updated for Q2 FY27 · checked 17 Nov 2026

This is the plain-text version of https://cityfort.in/stocks/rvnl. Source ids in [brackets] refer to the list at the end. Credit: "Cityfort, RVNL: how the business works", with the page URL.

## In short

Indian Railways and other public bodies pay RVNL to deliver projects; ₹90.6 of every ₹100 that came in during FY26 went on project work and materials, and ₹3.7 was left as profit.

- One customer, which the FY26 annual report does not name, gave 82.62% of FY26 revenue. The same report says RVNL's major client is Indian Railways.
- CARE says RVNL sub-contracts most construction work, and links its moderate profitability to that.

## Key facts

**What does RVNL do?**

Rail Vikas Nigam (RVNL), a government company set up in 2003 under the Ministry of Railways, plans and delivers railway projects such as new lines, doubling, electrification and workshops. It also builds metro, highway, port, energy and telecom projects. Its FY26 revenue was ₹20,412 crore. [S1]

**How does RVNL make money?**

RVNL earns revenue by executing projects, mostly through contractors it hires. CARE's March 2026 rating report says RVNL is paid its costs plus a fixed management margin on railway ministry projects given to it on nomination. RVNL also wins work in open bidding. Its FY26 profit for shareholders, as restated in the Q2 FY27 results, was ₹892 crore, 4.4% of revenue. [S39, S1, S58]

**Who are RVNL's customers?**

A single customer, which RVNL's FY26 annual report does not name, gave 82.62% of RVNL's FY26 consolidated revenue. The same annual report says RVNL's major client is Indian Railways, and that other clients include central and state government ministries, departments and public sector companies. [S1]

**How big is RVNL?**

RVNL had FY26 revenue of ₹20,412 crore and profit for shareholders of ₹892 crore, as restated in the Q2 FY27 results. The company said its order book, the value of work won but not yet done, was ₹93,492 crore on 30 Jun 2026. RVNL itself had 964 employees on 31 Mar 2026, 250 of them permanent. [S1, S58, S35, S41]

**Who owns RVNL?**

The Government of India, through the Ministry of Railways, owned 72.84% of RVNL on 30 Sep 2026. Indian institutions held 6.21%, foreign investors 2.37% and other shareholders 18.57%. No government shares were pledged. [S32]

**What is RVNL's order book?**

RVNL said its order book was ₹99,262 crore on 31 Mar 2026: about ₹45,000 crore given on nomination by the railway ministry, about ₹45,000 crore won in competitive bidding and about ₹9,262 crore of bids where it was the lowest bidder or held a letter of award. It said the order book was ₹93,492 crore on 30 Jun 2026. [S1, S35]

**Does RVNL have debt?**

RVNL had borrowings of ₹4,305 crore on 30 Sep 2026, against ₹4,814 crore on 31 Mar 2026. RVNL's FY26 annual report says most of the March figure was IRFC loans for railway ministry projects, which the ministry provides the money to repay, so they have no impact on RVNL's profit. CARE reaffirmed its CARE AAA (Stable) rating for RVNL on 9 Mar 2026. [S59, S58, S1, S39]

**How did RVNL do in Q2 FY27?**

In Q2 FY27 (Jul–Sep 2026), RVNL's revenue was ₹4,701 crore, down 8.2% from ₹5,123 crore a year earlier. Profit for shareholders rose 8.3%, to ₹249 crore. For Apr–Sep 2026, revenue was ₹9,022 crore, 0.1% lower than a year earlier, and profit for shareholders ₹409 crore, up 12.1%. [S59, S58, S10]

## What does RVNL sell?

RVNL is a government company that gets railway projects built. It designs and estimates them, hires contractors through tenders and manages the work until the line is commissioned. Since 2021 it also bids for metro, highway, port, transmission and irrigation work.

- **Railway projects:** New lines, doubling of tracks, gauge conversion, electrification, workshops and large bridges, mostly for the Ministry of Railways. Railway work was ₹16,865 crore, or 82.6% of FY26 revenue. [S1]
- **Projects won in open bidding:** Metros, highways, ports, transmission lines, irrigation and signalling work won against other bidders. CMD Saleem Ahmad said execution from bidding works was ₹6,283 crore in FY26. [S1, S36]
- **Energy and telecom:** Energy work brought ₹1,266 crore in FY26 and telecom ₹548 crore. RVNL is also building BharatNet, a ₹13,000 crore rural broadband project for BSNL. [S1, S35]
- **Work abroad:** Project units in the Maldives and Dubai. RVNL earned ₹909 crore outside India in FY26, 4.45% of revenue, from port (₹529 crore) and energy (₹380 crore) work. [S1]
- **Joint ventures:** Part-owned companies that own rail lines, roads and logistics parks. Kinet Railway Solutions, 25% owned, is to build 120 Vande Bharat sleeper trainsets under a ₹14,400 crore project with 35 years of maintenance. [S1, S35]

## Who pays RVNL?

- **One customer the annual report does not name (82.6% of revenue):** RVNL's FY26 accounts say 82.62% of consolidated revenue came from a single external customer in India. The share was 88.75% in FY24 and 93.63% in FY25. [S1, S2, S3]
- **All other customers (17.4% of revenue):** The rest of FY26 revenue, 17.38% (Cityfort calculation: 100% − 82.62%). It includes ₹909 crore earned outside India. [S1]
- **Customer concentration:** largest customer 82.6% of revenue. The FY26 customer note does not name the customer that gave 82.62% of revenue. Separately, the annual report says RVNL's major client is Indian Railways, and other clients include central and state government ministries, departments and public sector companies. [S1]

## Where the money went (FY26)

1. Clients paid RVNL ₹20,412 crore in FY26 for project work, and other income added ₹775 crore.
2. Project work and materials, mostly done by contractors, took ₹19,187 crore.
3. Staff cost ₹199 crore and other running costs ₹258 crore.
4. Interest was ₹419 crore; ₹406 crore of it was on IRFC loans, matched by ₹406 crore of interest income.
5. After depreciation (₹36 crore) and tax (₹311 crore), ₹777 crore was left. Joint ventures added ₹94 crore.

Sources: S1.

## Key numbers by year (₹ crore)

Financials: consolidated, ₹ crore. Financial year runs April to March (March year end). — = not shown on the page.

| Year | Revenue | EBITDA | EBITDA margin | Net profit | Net margin | EPS (₹ per share) | Operating cash flow | Capital spending | Free cash flow | Sources |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| FY22 (restated) | 19,382 | 1,214 | 6.3% | 1,110 | 5.7% | 5.32 | 4,793 | 14 | 4,779 | S4 |
| FY23 (restated) | 20,282 | 1,327 | 6.5% | 1,342 | 6.6% | — | −4,064 | 10 | −4,074 | S3 |
| FY24 (restated) | 21,879 | 1,434 | 6.6% | 1,551 | 7.1% | 7.44 | 2,956 | 116 | 2,839 | S2 |
| FY25 (restated) | 19,923 | 1,222 | 6.1% | 1,278 | 6.4% | 6.13 | 1,881 | 432 | 1,449 | S1 |
| FY26 (restated) | 20,412 | 879 | 4.3% | 892 | 4.4% | 4.28 | −1,889 | 61 | −1,950 | S1, S8, S58 |

- EBITDA = profit before interest, tax and wear-and-tear of assets.
- Net profit is the share belonging to the company's owners.

## Balance sheet (as of 31 Mar 2026, ₹ crore)

Most of RVNL's ₹4,814 crore of borrowings on 31 Mar 2026 were IRFC loans for ministry projects, which the ministry funds RVNL to repay. [S1, S39, S36, S58]

| Item | Value |
| --- | --- |
| Total debt | 4,814 |
| Cash and investments | 968 |
| Net debt (debt minus cash) | 3,846 |
| Net worth (shareholders' money) | 9,835 |
| Debt to equity (times) | 0.49 |

- The borrowings include ₹3,993 crore of IRFC loans taken for Ministry of Railways projects. The FY26 annual report says the ministry provides the money to service them, so they have no impact on RVNL's profit.
- CARE says that, leaving out these pass-through IRFC loans and interest-free ministry advances, RVNL's debt to tangible net worth was nil on 31 Mar 2025.
- Net debt = borrowings of ₹4,814 crore − cash of ₹556 crore and other bank balances of ₹412 crore = ₹3,846 crore (Cityfort calculation from the FY26 annual report).
- Money owed by customers was ₹5,370 crore on 31 Mar 2026, up from ₹1,782 crore a year earlier. CMD Saleem Ahmad said on 26 May 2026 that about ₹3,400 crore due from the ministry was received in April 2026.
- Krishnapatnam Railway Company, a joint venture, owed RVNL ₹1,116 crore on 31 Mar 2026, including ₹890 crore of interest.
- Claims not recorded as liabilities (standalone, 31 Mar 2026): contractors' arbitration claims of ₹4,979 crore and court cases of ₹467 crore. The annual report says such claims on ministry projects, if payable, form part of project cost and are reimbursable.
- Net worth is total equity of ₹9,835 crore; the part belonging to RVNL's shareholders was ₹9,839 crore (both as restated in the Q2 FY27 results).

## Who owns RVNL? (shareholding, Q2 FY27)

| Holder | % of shares |
| --- | --- |
| Promoters | 72.84% |
| Promoter shares pledged (% of promoter shares) | 0.0% |
| Foreign institutions (FII) | 2.37% |
| Indian institutions (DII) | 6.21% |
| Public | 18.57% |

Sources: S32, S31, S30, S29, S28, S27, S26, S25, S24, S23, S22, S21, S46.

## What could go wrong

### One customer gives most of the revenue

A single customer, which the annual report does not name, gave 82.62% of FY26 revenue. The share was 88.75% in FY24 and 93.63% in FY25. [S1, S2, S3, S39]

What to watch: The single-customer share in the FY27 annual report.

### Lower margins on bid work

CARE linked a lower FY25 margin mainly to more bid-based projects. Management said domestic bidding works earn 5–6%, against 8–10% for management-fee works. EBITDA fell from ₹6.6 per ₹100 of revenue in FY24 to ₹4.3 in FY26 (restated). [S39, S35, S1, S7, S58, S59]

What to watch: EBITDA margin each quarter, against 6.3% in Q2 FY27 and 4.4% in Q1 FY27.

### Slow payments from clients

Cash from operations was minus ₹1,889 crore in FY26 and ₹589 crore in Apr–Sep 2026, against minus ₹1,255 crore a year earlier. Money owed by customers was ₹5,530 crore on 30 Sep 2026, against ₹5,370 crore on 31 Mar 2026. CMD Saleem Ahmad named client payments as a challenge on 13 Aug 2026. [S1, S35, S59, S58]

What to watch: Cash from operations for FY27 and money owed by customers on 31 Mar 2027.

### Dues from a joint venture

Krishnapatnam Railway Company owed RVNL ₹1,047.08 crore on 30 Sep 2026 in the consolidated results, including ₹889.95 crore of interest; the auditor draws attention to it. The two are still discussing whether interest before 30 Sep 2024 is simple or compound. CARE says the joint venture is in arbitration with the South Central Railway zone over dues owed to it. [S58, S6, S39]

What to watch: The amount due in each results filing and any decision on how interest is charged.

### Contractor claims

Contractors' arbitration claims against RVNL were ₹4,979 crore on 31 Mar 2026, up from ₹4,528 crore a year earlier, and court cases ₹467 crore. The annual report says claims on ministry projects, if payable, are reimbursable project cost. [S1]

What to watch: Contingent liabilities in the FY27 annual report.

### Execution delays

Management said on 13 Aug 2026 that the BharatNet build will take another six to eight months. The CMD named the geopolitical situation and labour availability as challenges. [S35]

What to watch: Revenue each quarter against the order book of ₹93,492 crore on 30 Jun 2026.

### Board composition and leadership changes

NSE fined RVNL over board and committee composition for the Apr–Jun 2026 quarter. RVNL had three CMDs in FY26 and a Director (Finance) on additional charge from 30 Sep 2026. [S53, S1, S56]

What to watch: Board appointments by the Ministry of Railways and further exchange fines.

### Guarantee for a joint venture's loan

On 12 Nov 2026 RVNL's board approved a guarantee of up to ₹375 crore to Exim Bank for a ₹1,500 crore loan proposed for Kinet Railway Solutions, 25% owned by RVNL. RVNL said the guarantee costs it nothing unless Kinet defaults on the loan. [S58]

What to watch: Kinet's progress on the Vande Bharat sleeper trains and any further guarantees for joint ventures.

## What to watch

Next: Q3 FY27 results (date not announced; Q3 FY26 results came on 5 Feb 2026), Date not announced yet.

- **Q2 FY27 earnings call:** RVNL holds its Q2 FY27 call on 17 Nov 2026 at 4:00 pm IST. The Q2 results filing gives no order book figure for 30 Sep 2026.
- **The order book:** It was ₹99,262 crore on 31 Mar 2026 and ₹93,492 crore on 30 Jun 2026. Q1 FY27 order inflow was ₹5,417 crore.
- **Money owed by customers:** Receivables were ₹5,530 crore on 30 Sep 2026, against ₹5,370 crore on 31 Mar 2026 and ₹1,529 crore on 30 Sep 2025.
- **Margins against management's statements:** Cityfort's EBITDA margin was 6.3% in Q2 FY27 and 5.4% for Apr–Sep 2026. Management said on 13 Aug 2026 it expects about 15% revenue growth and 15–20% profit growth in FY27. In Apr–Sep 2026, revenue was 0.1% lower and profit 12.1% higher than a year earlier.
- **The Kinet guarantee:** RVNL's board approved a guarantee of up to ₹375 crore on 12 Nov 2026 for a loan to Kinet Railway Solutions, its 25% joint venture building Vande Bharat sleeper trains.

## Sources

- S1: Annual Report 2025-26 (FY26). Rail Vikas Nigam Ltd via NSE (revised upload 21 Aug 2026; first filed 1 Aug 2026). https://nsearchives.nseindia.com/annual_reports/AR_30506_RVNL_2025_2026_U_21279949_21082026184722.pdf (published 21 Aug 2026)
- S2: Annual Report 2024-25 (FY25). Rail Vikas Nigam Ltd via NSE (revised upload 22 Aug 2025). https://nsearchives.nseindia.com/annual_reports/AR_27588_RVNL_2024_2025_U_22082025200603.pdf (published 22 Aug 2025)
- S3: Annual Report 2023-24 (FY24). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/annual_reports/AR_26035_RVNL_2023_2024_06092024184042.pdf (published 6 Sep 2024)
- S4: Annual Report 2022-23 (FY23). Rail Vikas Nigam Ltd via NSE (zip). https://nsearchives.nseindia.com/annual_reports/AR_23287_RVNL_2022_2023_02092023172554_09022023180005.zip (published 2 Sep 2023)
- S5: Annual Report 2021-22 (FY22). Rail Vikas Nigam Ltd via NSE (zip). https://nsearchives.nseindia.com/annual_reports/AR_21721_RVNL_2021_2022_08092022174830.zip (published 8 Sep 2022)
- S6: Unaudited standalone and consolidated results, quarter ended 30 Jun 2026 (Q1 FY27), with limited review reports. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_11082026143057_Outcome_BOD_Q130062026.pdf (published 11 Aug 2026)
- S7: Consolidated financial results XBRL, Q1 FY27 (quarter to 30 Jun 2026). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INTEGRATED_FILING_INDAS_1711789_11082026052009_WEB.xml (published 11 Aug 2026)
- S8: Consolidated financial results XBRL, Q4 FY26 and FY26 (audited, to 31 Mar 2026). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INTEGRATED_FILING_INDAS_1672816_25052026102416_WEB.xml (published 25 May 2026)
- S9: Consolidated financial results XBRL, Q3 FY26 (quarter to 31 Dec 2025). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INTEGRATED_FILING_INDAS_1619262_05022026055013_WEB.xml (published 5 Feb 2026)
- S10: Consolidated financial results XBRL, Q2 FY26 (quarter and half year to 30 Sep 2025). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INTEGRATED_FILING_INDAS_1571725_11112025084530_WEB.xml (published 11 Nov 2025)
- S11: Consolidated financial results XBRL, Q1 FY26 (quarter to 30 Jun 2025). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INTEGRATED_FILING_INDAS_1509791_12082025053139_WEB.xml (published 12 Aug 2025)
- S12: Consolidated financial results XBRL, Q4 FY25 and FY25 (audited, to 31 Mar 2025). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INTEGRATED_FILING_INDAS_1446261_21052025082338_WEB.xml (published 21 May 2025)
- S13: Consolidated financial results XBRL, Q3 FY25 (quarter to 31 Dec 2024). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INDAS_120772_1385570_14022025090103.xml (published 14 Feb 2025)
- S14: Consolidated financial results XBRL, Q2 FY25 (quarter and half year to 30 Sep 2024). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INDAS_114439_1300652_07112024092137.xml (published 7 Nov 2024)
- S15: Consolidated financial results XBRL, Q1 FY25 (quarter to 30 Jun 2024). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INDAS_110823_1217180_08082024052909.xml (published 8 Aug 2024)
- S16: Consolidated financial results XBRL, Q4 FY24 and FY24 (audited, to 31 Mar 2024). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INDAS_106311_1129131_17052024100715.xml (published 17 May 2024)
- S17: Consolidated financial results XBRL, Q3 FY24 (quarter to 31 Dec 2023). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INDAS_102842_1048637_08022024062623.xml (published 8 Feb 2024)
- S18: Consolidated financial results XBRL, Q2 FY24 (quarter and half year to 30 Sep 2023). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INDAS_100204_984624_10112023010858.xml (published 10 Nov 2023)
- S21: Shareholding pattern as of 31 Dec 2023 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_184798_1027480_18012024054419_WEB.xml (published 18 Jan 2024)
- S22: Shareholding pattern as of 31 Mar 2024 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_187853_1101174_19042024041821_WEB.xml (published 19 Apr 2024)
- S23: Shareholding pattern as of 30 Jun 2024 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_189970_1191036_18072024011131_WEB.xml (published 18 Jul 2024)
- S24: Shareholding pattern as of 30 Sep 2024 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_192217_1271816_16102024124238_WEB.xml (published 16 Oct 2024)
- S25: Shareholding pattern as of 31 Dec 2024 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_195169_1349772_17012025054942_WEB.xml (published 17 Jan 2025)
- S26: Shareholding pattern as of 31 Mar 2025 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_197836_1417800_17042025065951_WEB.xml (published 17 Apr 2025)
- S27: Shareholding pattern as of 30 Jun 2025 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_1487076_18072025063916_WEB.xml (published 18 Jul 2025)
- S28: Shareholding pattern as of 30 Sep 2025 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_1554616_21102025103759_WEB.xml (published 21 Oct 2025)
- S29: Shareholding pattern as of 31 Dec 2025 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_1605135_20012026121731_WEB.xml (published 20 Jan 2026)
- S30: Shareholding pattern as of 31 Mar 2026 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_1652990_17042026013727_WEB.xml (published 17 Apr 2026)
- S31: Shareholding pattern as of 30 Jun 2026 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_1696996_20072026045622_WEB.xml (published 20 Jul 2026)
- S32: Shareholding pattern as of 30 Sep 2026 (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_1741297_19102026013046_WEB.xml (published 19 Oct 2026)
- S34: Shareholding pattern as of 28 Jul 2023 (after the GoI offer for sale) (XBRL). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/xbrl/SHP_180321_907483_03082023062123_WEB.xml (published 3 Aug 2023)
- S35: Transcript of Q1 FY27 earnings call held on 13 Aug 2026. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_18082026141230_Transcriptcovering.pdf (published 18 Aug 2026)
- S36: Transcript of Q4 FY26 earnings call held on 26 May 2026. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_02062026124525_Transcriptcovering.pdf (published 2 Jun 2026)
- S37: Transcript of Q3 FY26 earnings call held on 6 Feb 2026. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_09022026180837_Transcriptcovering.pdf (published 9 Feb 2026)
- S38: Transcript of Q2 FY26 earnings call held on 12 Nov 2025. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_17112025170137_Transcriptcovering.pdf (published 17 Nov 2025)
- S39: CareEdge press release: Rail Vikas Nigam Limited, CARE AAA; Stable / CARE A1+ (reaffirmed; ₹1,510 cr assigned). CARE Ratings Limited. https://www.careratings.com/upload/CompanyFiles/PR/202603120334_Rail_Vikas_Nigam_Limited.pdf (published 9 Mar 2026)
- S40: Intimation of credit rating obtained from CareEdge. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_05032026172346_Covering_Credit_rating_05032026.pdf (published 5 Mar 2026)
- S41: Business Responsibility and Sustainability Report FY 2025-26 (standalone). Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_01082026165629_BRSRreport.pdf (published 1 Aug 2026)
- S42: Audited standalone and consolidated results, quarter and year ended 31 Mar 2026 (Q4 FY26), with final dividend recommendation. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_25052026180000_Outcome_BOD_Q431032026.pdf (published 25 May 2026)
- S43: SAST Reg 29(2) disclosure by the President of India (Ministry of Railways): sale of 111,757,077 shares in the offer for sale of 27-28 Jul 2023. Ministry of Railways via NSE. https://nsearchives.nseindia.com/corporate/RVNL_07312023193600_1.zip (published 31 Jul 2023)
- S44: SAST Reg 29(2) disclosure by the President of India (Ministry of Railways): sale of 200,933,926 shares in the offer for sale of 24-25 Mar 2021. Ministry of Railways via NSE. https://nsearchives.nseindia.com/corporate/SAST_03302021085205_2.zip (published 30 Mar 2021)
- S46: SAST Reg 31(4) declaration by Ministry of Railways: 1,518,743,694 shares held at 31 Mar 2026, no encumbrance in FY26. Ministry of Railways via NSE. https://nsearchives.nseindia.com/corporate/team_bbodade_05052026162332_RVNL.pdf (published 26 May 2026)
- S48: Intimation of board meeting on 13 Nov 2026 for Q2 FY27 / H1 results. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_04112026112510_BODIntimation30092026.pdf (published 4 Nov 2026)
- S49: Board meeting for Q2 FY27 results rescheduled to Thursday 12 Nov 2026. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_09112026174457_BODIntimation30092026.pdf (published 9 Nov 2026)
- S50: Invite for Q2 FY27 investor conference call on Tuesday 17 Nov 2026, 4:00 pm IST. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_11112026180134_Concallintimation.pdf (published 11 Nov 2026)
- S52: C&AG appoints Gandhi Minocha & Co. as statutory auditor for FY 2026-27. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_09092026180635_Appoitment09092026.pdf (published 9 Sep 2026)
- S53: Fine of ₹9,66,420 by NSE for board/committee composition, quarter ended 30 Jun 2026. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_26082026151652_Finedetails26082026.pdf (published 26 Aug 2026)
- S55: Ministry of Railways entrusts additional charge of Director (Finance) to Neeti Sarkar. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_29092026180956_Covering29092026.pdf (published 29 Sep 2026)
- S56: Change in director: Neeti Sarkar Director (Finance) w.e.f. 30 Sep 2026; Abhishek Kumar ceases. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_30092026164406_Covering30092026.pdf (published 30 Sep 2026)
- S57: NSE full bhavcopy for 11 Nov 2026 (RVNL, EQ series closing price). National Stock Exchange of India. https://nsearchives.nseindia.com/products/content/sec_bhavdata_full_11112026.csv (published 11 Nov 2026)
- S58: Unaudited standalone and consolidated results, quarter and half year ended 30 Sep 2026 (Q2 FY27), with limited review reports and corporate guarantee details. Rail Vikas Nigam Ltd via NSE. https://nsearchives.nseindia.com/corporate/RVNL_12112026194551_Outcome_BOD_Q230092026.pdf (published 12 Nov 2026)
- S59: Consolidated financial results XBRL, Q2 FY27 (quarter and half year to 30 Sep 2026). Rail Vikas Nigam Ltd via NSE (XBRL filing). https://nsearchives.nseindia.com/corporate/xbrl/INTEGRATED_FILING_INDAS_1756948_12112026080640_WEB.xml (published 12 Nov 2026)
- S60: NSE full bhavcopy for 13 Nov 2026 (RVNL, EQ series closing price). National Stock Exchange of India. https://nsearchives.nseindia.com/products/content/sec_bhavdata_full_13112026.csv (published 13 Nov 2026)